SPECIFICATION S.1
Boiler tappings are one-off flanged flow and return connections and
seven tappings which are fitted on top of the boiler to accommodate altitude
gauge, thermometer, air vent, safety valves, limit and control thermostats. A
drain cock is mounted at the rear of the boiler. A control high limit dual
thermostat is supplied as standard pre-wired and a short flexible oil
connection and strainer. An Electronic temperature controller, combining operating
and limit function complete with type K Thermo couple located in common flow
header can be supplied as an optional extra.
SPECIFICATION
S.2
This boiler unit is fully packaged, all as S.1, but
includes mountings and meets relevant Ministry specifications, with particular
reference to M & E 3. Thermostats are supplied as standard, pre‑wired
together with short flexible oil connection and strainer. Packaged unit includes
boilers with fully insulated casings up to 10Omm and/or to the relevant British
Standard. Boiler tappings are one-off flanged flow and return connections
and seven tappings with fitted altitude gauge, thermometer, safety valve and
control and limit dual thermostat in pocket, open air vent, spare tapping for
high/low thermostat.
SPECIFICATION
S.4
Boiler only otherwise all as S. 1, supplied with easing and
boiler front plate to suit burners being supplied by customer.
SPECIFICATION S.5
Comprehensive boiler to any of above specifications
complete with mixing shunt pump and all interconnecting pipe work, valves and
fittings. Details on request.
SPECIFICATION
S.6
Boilers supplied to any of the above specifications as
combination units complete with hot water cylinders. Details on request.
COMPACT
DESIGN
The EASYFIRE SHELL 3 pass wet back boiler with pressurised
combustion chamber is designed to allow the first and second passes of gas to be
made within the chamber. The boiler is designed with a unique third pass heat
exchange (Kayanson 'CONVECTION' design) to ensure a minimum of 80% efficiency.
BOILER
MAINTENANCE
The oil or gas burner supplied is mounted on a firing door,
which is insulated together with a refractory lining and seal on the inside of
boiler. In addition, a hinged door is provided at front of boiler for access to
the third pass, together with an inspection plate at rear of boiler. Dual
left/right hand opening supplied as standard.
QUALITY
AND EFFICIENCY
Units, insulated to the relevant British Standards, are
working under pressurised combustion overcoming light‑up or cold start
resistance. Each boiler is constructed from boiler quality steel plates and
complies to all the relevant International, British and Ministry standards.
Quality has been assessed by BSI Quality Assurance Service to BS5750,
certificate No. FM 1566.
Tables
Minimum static head all models three metres. Minimum
clearance: at front for burner projection; at rear for pipe work only; at sides
no clearance necessary. Please contact
our drawing office for more specific information. All dimensions and
relevant connections are in mm
Minimum static head all
models three metres.
Minimum clearance: at
front for burner protection; at rear for pipework only; at sides no clearance
necessary.
Please contact our technical dept for more specific
information. All dimensions and relevant connections are in mm.